Morley station: Buses to replace trains in Leeds for four weeks as 4000m of new track and cabling installed

Trains in Leeds are to face a month of service disruption as major network upgrades get underway.
Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now

Changes to weekday services between Huddersfield, Dewsbury and Leeds will be in place for a four-week period from Monday, April 22 until Friday, May 17, as TRU complete major upgrades.

Throughout the work, a total of 4000m of new track will be installed between Morley and Cottingley station while troughing will be fitted to hold 3500m of new signal cables.

Hide Ad
Hide Ad

While this takes place, engineers will also remove five redundant signal bases and undertake some work to the platforms at Morley station.

Changes to weekday services between Huddersfield, Dewsbury and Leeds will be in place for a four-week period. Pictures: PA/Network RailChanges to weekday services between Huddersfield, Dewsbury and Leeds will be in place for a four-week period. Pictures: PA/Network Rail
Changes to weekday services between Huddersfield, Dewsbury and Leeds will be in place for a four-week period. Pictures: PA/Network Rail

Chris Nutton, Major Projects Directors at TransPennine Express, said: “The major upgrade works that will be done between Huddersfield and Leeds over this four-week period are essential for the delivery of more reliable services for our customers.

“We will be running an amended timetable on our North route while these improvement works are being carried out, diverting trains between Huddersfield and Leeds.

“Rail replacement buses will also be in place to keep customers on the move for more local journeys. We’d like to advise customers to check before they travel.”

Hide Ad
Hide Ad

Environmental and ground surveys will be completed, including bat surveys, trial pits and coring work, in advance of future work along the route.

Diversionary routes and rail replacement buses will keep people on the move, but passengers are advised to plan ahead and check nationalrail.co.uk before travelling.

The work is part of the Transpennine Route Upgrade, a multi-billion pound programme of rail upgrades between Manchester, Huddersfield, Leeds and York.

TransPennine Express:

  • Services between Huddersfield – Leeds will be diverted and will not run through Dewsbury.
  • Rail replacement bus services will replace services between Huddersfield – Dewsbury – Leeds.
  • Services from Hull will start/terminate at Leeds.
  • Services from Saltburn to Manchester Airport will start/terminate at Manchester Victoria.
  • Rail replacement buses will operate between Huddersfield – Manchester Airport via Stockport

Northern:

  • Services between Leeds – Wigan via Brighouse will be diverted and will not run through Dewsbury.
  • Rail replacement bus services will run between Halifax – Brighouse – Dewsbury – Leeds

Services between Marsden – Huddersfield – Heaton Lodge will also be affected on Saturdays and Sundays over the following weekend.