Parts of the newly redesigned entrance at Leeds station is expected to begin opening next month - despite being hit by more delays.
Having originally been due to be completed by September 2025, the revamped New Station Street entrance at Leeds City Station, is projected to begin opening in early to mid-October.
The £46.1 million improvement scheme has faced a series of delays as a result of complex works. However, partners are working together to negotiate the earlier opening of some elements of the scheme in advance of full completion.
Take a look below at how the site is beginning to take shape...
7. Leeds station revamp
The scheme has been built at the same time as essential maintenance by Network Rail to reinforce the underground Mill Goit structure below New Station Street. | Gerard Binks
8. Leeds station revamp
Network Rail, as the asset owner, will take over the scheme once it is completed. | Gerard Binks
9. Leeds station revamp
Lifts, providing step-free access between New Station Street and Bishopgate Street, are expected to open in mid-October. | Gerard Binks
10. Leeds station revamp
The cycle hub lifts are expected to open in late October. | Gerard Binks
11. Leeds station revamp
The entrance’s 'Welcome to Leeds' clocktower centrepiece has been the focus of much online debate in recent months, after a few eagle-eyed residents spotted a potential lettering error and alignment fault. | Gerard Binks