Yorkshire Water spending £36m on new 'storm water storage' in Leeds including Pudsey, Drighlington and Farnley

Yorkshire Water has announced it will spend £36m on new "storm water storage" in Leeds.
Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now

The investment will affect areas including Pudsey, Drighlington and Farnley, and aims to improve water quality by reducing storm overflows when their is heavy rain.

It will see approximately 18,250m3 of additional storage added to the network to slow the flow of heavy or prolonged rainfall, which it has been suggested will reduce the number of storm discharges into Pudsey Beck by more than 20%.

The six new projects include:

Hide Ad
Hide Ad
Artist impression of Hough Side integrated constructed wetland. Photo: Yorkshire Water.Artist impression of Hough Side integrated constructed wetland. Photo: Yorkshire Water.
Artist impression of Hough Side integrated constructed wetland. Photo: Yorkshire Water.
  • New storm water storage at Pudsey Smalewell, which will begin in October.
  • New storm water storage at Farnley ring road beginning in January.
  • Installation of storm water storage at Kent Road, Littlemoor Bottom, Pudsey beginning in February.
  • Installation of storm water storage at Dale Farm, Drighlington, beginning in February.
  • Additional storm water storage off Dick Lane, Thornbury, Bradford beginning in January.
  • The creation of a 4.7-hectare integrated constructed wetland at a disused Yorkshire Water site previously earmarked for housing at Hough Side, Pudsey beginning in July.

The new integrated constructed wetland at Hough Side will accommodate a minimum 25,000m3 of diluted wastewater from heavy or prolonged rainfall events and will take approximately three years to construct.

Plants in a series of cells will treat the diluted wastewater as it travels through the wetland via gravity. Pollutants and nutrients will be naturally broken down and taken up by the plants and bacteria within the wetland. The wastewater will not include solid waste.

Once established, it is expected that the wetland will provide a biodiversity net gain and improve the area for wildlife.

Richard Stuart, director of capital delivery at Yorkshire Water, said: “We are committed to improving water quality in the rivers across our region. One of the key focuses is reducing storm overflows to make a real difference to water quality in our rivers.

Hide Ad
Hide Ad

“This project is a significant investment in the west Leeds and Bradford areas to improve water quality within Pudsey Beck. The additional storage and wetland we are building into the network will reduce the number of storm overflows significantly into the watercourse and is just part of a £568m capital investment we are making across Yorkshire this year alone.

“While work is being conducted in the area, there may be some traffic disruption and we are working closely with local authority highways departments to ensure disruption is kept to a minimum.

“We know that there is more to be done to tackle storm overflows. We are already working on our largest ever environmental investment as part of our 2025-2030 business plan.

"The plans, which will be subject to approval by our regulator Ofwat, outline a £1 billion investment to further reduce discharges from overflows to meet the government’s storm overflow reduction plan, including the requirement for coastal bathing waters of an average of two spills per bathing water season by 2035.”

Hide Ad
Hide Ad

The project is a collaboration between Yorkshire Water, Stantec, Kier, Arup, WSP, Mott MacDonald Bentley, Peter Duffy Limited, Galliford Try, Barhale, Tilbury Douglas, Leeds City Council and Bradford Metropolitan District Council.